Citywide Projects
UPDATE: 04/01/25- This project is still in the utility relocation phase. Utility providers will be on the right-of-way of both sides of Telephone Rd. moving their lines in preparation for the widening. There is no scheduled start time as it is dependent on the relocation efforts.
The project will consist of removal and replacement of sub-grade and base materials, as well as replacement of the existing driving surface with concrete between SW 19th Street and SW 34th Street. Including necessary curb and guttering, storm drainage improvements, sidewalks, streetscape and utility line replacement. Telephone Road will also be widened to from 4-lanes to 5-lanes. This is a $10.9 million project.

UPDATE: 05/13/2025- This project has been completed and Indian Hills is open.
Per the City of Norman; Indian Hills between N. Blue Lake Drive and 12th Avenue NW will be closed, effective immediately, due to safety concerns. Repairs will be to replace the cross drain pipe. Indian Hills should be reopened by Monday, May 12, 2025, weather permitting.
UPDATE: 05/08/2025: Crews are hoping to have this project wrapped up by the end of next week, May 16, weather permitting.
UPDATE 3/27/2025: The road is now open but there is still some construction remaining in the area.
UPDATE 2/14/2025: Due to the inclement weather, the opening of Bryant Ave will be pushed back to the end of March 2025.
UPDATE 1/17/2025: The draining work is complete. Beginning, January 20, 2025, weather permitting, Silverstar will begin demolition of Bryant Ave. for reconstruction of the street. It is anticipated that the reconstruction of the street will be completed by the end of February. Construction of the bicycle/pedestrian trail and cleanup of the project area should be completed by the middle of March.
UPDATE 12/30/2024: Silverstar Construction will be finishing up the drainage project side next week.
UPDATE 10/24/2024: Beginning Monday, October 28, the jersey barriers will be removed on Bryant. Channel work will begin on the west side of Bryant, therefore crews must again close Bryant while work is being completed. Completion date is first quarter of 2025, weather permitting.
UPDATE 10/1/2024: Jersey barriers were setup to open southbound only traffic on Bryant. Crews will start on the east side of the creek mid-week and complete that side before moving to the west side.
UPDATE 08/26/24: There is a delay in opening Bryant Ave to SE 4th St. The heavy rains received over the past 6 weeks have caused the bottom of the channel to become unstable due to the continued inflow of groundwater from the bottom and sides of the channel. A stable bottom is necessary to support the structural improvements. The design engineer is working on a solution to address the groundwater inflow. Once the solution is finalized an update will be posted here. Also, once we have a completion date, we will update it here.
Beginning Wednesday, May 22, 2024, Bryant Ave will be closed from Parkway Dr. to SE 4th St. This will be a construction of drainage improvements on the east side of Bryant Ave.
05/08/2025 UPDATE: This project is currently set to be completed by the end of June. OKC has not accounted for all the weather delays in April, so it could run into July. They are hoping for a June completion, weather permitting.
04/09/25 UPDATE: Per the City of OKC, SW 149th Street from Hudson Avenue to Vicki Drive will temporarily close to traffic from Friday, April 11, to Saturday, April 12. Crews are working on a storm sewer drain as part of the street widening project.
08/19/2024 UPDATE: Beginning Wednesday, August 21, 2024 Westmore Dr will be closed until May 2025. The project construction manager has recognized potential safety concerns and has advised the City of Moore to close the street.
07/23/2024 Beginning Tuesday evening after 8:00pm, the Contractor performing the construction for the Widening of 149th Street in OKC from Santa Fe to Western will be closing lanes at the intersection of SW 19th St. and Santa Fe Ave. in Moore. For Westbound traffic at the intersection, the existing left turn lane will be closed. The existing westbound thru lane will be used for thru traffic as well as the left turn lane for traffic turning south during construction. For Eastbound traffic at the intersection, the existing left turn lane will be closed. The existing outside eastbound lane will be used for thru traffic as well as the left turn lane for traffic turning north. The existing inside eastbound lane will now become the westbound lane for thru traffic. Double yellow striping will separate the eastbound and westbound traffic west of the intersection during construction. It is anticipated that construction will take approximately 8 months to complete. Any questions regarding the project should be addressed with the OKC Project Construction Manager at 405-297-1768 or [email protected]
Update: 5/15/2025 Briarhill Dr is open! Crews are finishing up and sod will be laid next week.
Update: 5/8/2025 Briarhill should be opened next Thursday, May 15, weather permitting.
Update: 4/17/2025 The Briarhill box has been poured and crews are now backfilling. The next step will be street paving and cure time for the bridge. The project should be completed in 2 weeks, weather permitting.
Update: 4/10/2025 Crews are pouring the bridge deck this morning. The project should be completed 3 weeks from today, weather permitting.
Update: 3/31/2025 Progress is being made. Crews will be pouring the walls tomorrow. Approximate opening date will be 5 weeks, weather permitting.
Update: 3/13/2025 Briarhill remains closed. The estimated time of reopen is end of April, weather permitting.
Briarhill is closed between NE 19th & NE 20th for an indefinite period of time due to bridge failure.
05/19/2025: SW 34th & Santa Fe Ave- OKC Water Department will have the west side outside lane of Santa Fe closed for waterline repairs from last weeks water main break. This will be closed for an unknown amount of time.
05/15/2025: Sam's Club, Taco Bell, Braum's, & McDonald's- Crews will be installing a new sewer main & 2 manholes in this area. This project will take about 2 weeks, weather permitting.
05/13/2025: Arnold Street- Arnold St is being totally reconstructed from NW 5th St to NW 2nd St. Project will be 3 weeks, weather permitting.
05/08/2025: Phillips Blvd.- Concrete panels will be replaced on both sides starting May 12th. Phillips Blvd will remain open. Estimated completion date is 2 weeks, weather permitting.
UPDATE: 05/15/2025- Progress is being made. Still a couple of weeks out to complete the project, weather permitting.
04/10/2025- Norman St, between Main St & SW 1st St crews will start a reconstruction of Norman St. Completion date is 2 weeks, weather permitting.
UPDATE: 05/15/2025- The west side of the street is complete, waiting on it to cure & dry. The east side will start next week, it will take a couple weeks, weather permitting.
UPDATE: 05/08/2025- This project has been delayed due to weather. It started on May 7th and should be completed in 2 weeks, weather permitting.
UPDATE: 04/24/2025- Norman St has been delayed due to the high probability of rain over the next week. This project should start up mid-week next week.
03/15/2025- Sunrise Dr- Crews will be installing new water main lines on Sunrise Dr, NW 24th St, N Janeway Ave & Vermeer Dr. This project is expected to be complete by July 30, 2025, weather permitting.
Buck Thomas Park Football Fields:
05/08/2025- Crews will be working on drainage issues for the football fields at Buck Thomas Park. Construction is set to begin the beginning of June 2025 with the completion date set for the end of June 2025, weather permitting.
Kiwanis Park:
05/08/2025- Crews will be working on adding a sidewalk from the parking lot directly to the front entrance of the pickle ball courts. The Crews will also be making sidewalk repairs in front of the Brand Senior Center. Construction is set begin by the end of May 2025 with the completion date set for mid- June 2025, weather permitting.
Urbansky Farms; nearest intersection is S.E. 19th & Sunnylane Rd.
Update: 05/15/2025- Bridge work is completed. Crews will be pouring drainage channel for the pond overflow.
Cypress Creek; nearest intersection is S.E. 19th & Sunnylane Rd.
Update: 04/10/2025- Crews are pouring the approach on SE 19th St
Flicker Ridge; nearest intersection is N.E. 12th & Flicker Ridge.
Update: 05/15/2025- Sewerlines will be installed this week.
Broadmoore Heights; nearest intersection is S.E. 34th & S Bryant Ave.