Citywide Projects

UPDATE: 04/01/25- This project is still in the utility relocation phase. Utility providers will be on the right-of-way of both sides of Telephone Rd. moving their lines in preparation for the widening. There is no scheduled start time as it is dependent on the relocation efforts.

The project will consist of removal and replacement of sub-grade and base materials, as well as replacement of the existing driving surface with concrete between SW 19th Street and SW 34th Street.  Including necessary curb and guttering, storm drainage improvements, sidewalks, streetscape and utility line replacement.  Telephone Road will also be widened to from 4-lanes to 5-lanes. This is a $10.9 million project. 

SW 19th st to SW 34th St

Per the City of Norman; Indian Hills between N. Blue Lake Drive and 12th Avenue NW will be closed, effective immediately, due to safety concerns. Repairs will be to replace the cross drain pipe. Indian Hills should be reopened by Monday, May 12, 2025, weather permitting.

UPDATE: 05/08/2025: Crews are hoping to have this project wrapped up by the end of next week, May 16, weather permitting.

UPDATE 3/27/2025: The road is now open but there is still some construction remaining in the area.

UPDATE 2/14/2025:  Due to the inclement weather, the opening of Bryant Ave will be pushed back to the end of March 2025.

UPDATE 1/17/2025: The draining work is complete. Beginning, January 20, 2025, weather permitting, Silverstar will begin demolition of Bryant Ave. for reconstruction of the street.  It is anticipated that the reconstruction of the street will be completed by the end of February.  Construction of the bicycle/pedestrian trail and cleanup of the project area should be completed by the middle of March.

UPDATE 12/30/2024: Silverstar Construction will be finishing up the drainage project side next week.  

UPDATE 10/24/2024: Beginning Monday, October 28, the jersey barriers will be removed on Bryant.  Channel work will begin on the west side of Bryant, therefore crews must again close Bryant while work is being completed.  Completion date is first quarter of 2025, weather permitting.

UPDATE 10/1/2024: Jersey barriers were setup to open southbound only traffic on Bryant. Crews will start on the east side of the creek mid-week and complete that side before moving to the west side. 

UPDATE 08/26/24: There is a delay in opening Bryant Ave to SE 4th St. The heavy rains received over the past 6 weeks have caused the bottom of the channel to become unstable due to the continued inflow of groundwater from the bottom and sides of the channel.  A stable bottom is necessary to support the structural improvements. The design engineer is working on a solution to address the groundwater inflow. Once the solution is finalized an update will be posted here.  Also, once we have a completion date, we will update it here.

Beginning Wednesday, May 22, 2024, Bryant Ave will be closed from Parkway Dr. to SE 4th St. This will be a construction of drainage improvements on the east side of Bryant Ave.  

05/08/2025 UPDATE: This project is currently set to be completed by the end of June. OKC has not accounted for all the weather delays in April, so it could run into July. They are hoping for a June completion, weather permitting.

04/09/25 UPDATE: Per the City of OKC, SW 149th Street from Hudson Avenue to Vicki Drive will temporarily close to traffic from Friday, April 11, to Saturday, April 12. Crews are working on a storm sewer drain as part of the street widening project.

08/19/2024 UPDATE: Beginning Wednesday, August 21, 2024 Westmore Dr will be closed until May 2025.  The project construction manager has recognized potential safety concerns and has advised the City of Moore to close the street.

07/23/2024  Beginning Tuesday evening after 8:00pm, the Contractor performing the construction for the Widening of 149th Street in OKC from Santa Fe to Western will be closing lanes at the intersection of SW 19th St. and Santa Fe Ave. in Moore.  For Westbound traffic at the intersection, the existing left turn lane will be closed.  The existing westbound thru lane will be used for thru traffic as well as the left turn lane for traffic turning south during construction.  For Eastbound traffic at the intersection, the existing left turn lane will be closed.  The existing outside eastbound lane will be used for thru traffic as well as the left turn lane for traffic turning north.  The existing inside eastbound lane will now become the westbound lane for thru traffic.  Double yellow striping will separate the eastbound and westbound traffic west of the intersection during construction.  It is anticipated that construction will take approximately 8 months to complete.  Any questions regarding the project should be addressed with the OKC Project Construction Manager at 405-297-1768 or [email protected]

Update: 5/8/2025 Briarhill should be opened next Thursday, May 15, weather permitting.

Update: 4/17/2025 The Briarhill box has been poured and crews are now backfilling.  The next step will be street paving and cure time for the bridge.  The project should be completed in 2 weeks, weather permitting.

Update: 4/10/2025 Crews are pouring the bridge deck this morning.  The project should be completed 3 weeks from today, weather permitting.

Update: 3/31/2025 Progress is being made.  Crews will be pouring the walls tomorrow.  Approximate opening date will be 5 weeks, weather permitting.

Update: 3/13/2025 Briarhill remains closed.  The estimated time of reopen is end of April, weather permitting.

Briarhill is closed between NE 19th & NE 20th for an indefinite period of time due to bridge failure.
 

05/08/2025- Phillips Blvd. Concrete panels will be replaced on both sides starting May 12th.  Phillips Blvd will remain open.  Estimated completion date is 2 weeks, weather permitting.

05/02/2025- The Waters Neighborhood (NE 34th & NE 33rd and N Eastern Ave) road repairs

Starting Monday, May 5, 2025 crews will begin some deep asphalt patching repairs.  All streets should remain open throughout the neighborhood. This project should last 10-14 days, weather permitting.

UPDATE: 05/08/2025- This project was slightly delayed due to the rainy weather.  It started on May 7th and is expected to be completed in 10-14 days, weather permitting.

04/10/2025- Norman St, between Main St & SW 1st will be starting a reconstruction.  Completion date is 2 weeks, weather permitting.

UPDATE: 04/24/2025- Norman St has been delayed due to the high probability of rain over the next week.  This project should start up mid-week next week.

UPDATE: 05/08/2025- This project has been delayed due to weather.  It started on May 7th and should be completed in 2 weeks, weather permitting.

04/07/2025- Post Oak Road, panel repair work, 2-3 weeks for completion. 

UPDATE: 04/17/2025- Post Oak Project has been completed on one side of the street.  The other half of the street should be torn out next Monday, April 21, 2025.  Completion date is next week, weather permitting.

UPDATE: 05/08/2025- COMPLETED

03/15/2025- Crews will be installing new water main lines on Sunrise Dr, NW 24th St, N Janeway Ave & Vermeer Dr. This project is expected to be complete by July 30, 2025, weather permitting.

Buck Thomas Park Football Fields:
05/08/2025- Crews will be working on drainage issues for the football fields at Buck Thomas Park.  Construction is set to begin the beginning of June 2025 with the completion date set for the end of June 2025, weather permitting. 

Kiwanis Park:
05/08/2025- Crews will be working on adding a sidewalk from the parking lot directly to the front entrance of the pickle ball courts.  The Crews will also be making sidewalk repairs in front of the Brand Senior Center.  Construction is set begin by the end of May 2025 with the completion date set for mid- June 2025, weather permitting.

The Station Pool:
UPDATE: 05/08/2025- Due to the weather, the completion date of the repainting of the Station pool has been pushed back to Wednesday, May 14, 2025, weather permitting.

04/17/2025- The City has contracted Handy Dandy Handyman Inc. to repaint the Station pool for the upcoming pool season.  Completion date is Friday, April 25th, weather permitting.

Veterans Memorial Park Trail Enhancements:
UPDATE: 05/02/2025- Due to the weather, the completion date of the trail enhancements have been delayed.  This project should be completed by mid- May 2025, weather permitting.

UPDATE: 03/18/2025 This project is nearing completion and should be finalized by mid-April, 2025, weather permitting.

02/01/2025- Construction of concrete flatwork, site signage, and the purchase and installation of benches and tables. We will be adding a shelter, granite walks and edge restraints, trees, and landscape beds.  This will be funded by a grant the Oklahoma Recreational Trails Grant for 80% to 20% city match that the City received.  

Little River Park Trail Relocation & Repairs:  
02/03/2025- Crews are currently working on relocating the trail in the middle of the park on the furthest west side that runs closest to the creek.  It is being relocated because of the washing out of the creek and safety concerns of the proximity of the trail to the edge of the creek has continued to get closer over time.  Also, crews will be working on repairing other areas of the trail that have cracked over time.  Completion date is Friday, May 16th, weather permitting.

Urbansky Farms; nearest intersection is S.E. 19th & Sunnylane Rd.

Cypress Creek; nearest intersection is S.E. 19th & Sunnylane Rd.

Update: 04/10/2025 Crews are pouring the approach on SE 19th St

Flicker Ridge; nearest intersection is N.E. 12th & Flicker Ridge.

Broadmoore Heights; nearest intersection is S.E. 34th & S Bryant Ave.