Citywide Projects

UPDATE: 04/01/25- This project is still in the utility relocation phase. Utility providers will be on the right-of-way of both sides of Telephone Rd. moving their lines in preparation for the widening. There is no scheduled start time as it is dependent on the relocation efforts.

The project will consist of removal and replacement of sub-grade and base materials, as well as replacement of the existing driving surface with concrete between SW 19th Street and SW 34th Street.  Including necessary curb and guttering, storm drainage improvements, sidewalks, streetscape and utility line replacement.  Telephone Road will also be widened to from 4-lanes to 5-lanes. This is a $10.9 million project. 

SW 19th st to SW 34th St

05/08/2025 UPDATE: This project is currently set to be completed by the end of June. OKC has not accounted for all the weather delays in April, so it could run into July. They are hoping for a June completion, weather permitting.

04/09/25 UPDATE: Per the City of OKC, SW 149th Street from Hudson Avenue to Vicki Drive will temporarily close to traffic from Friday, April 11, to Saturday, April 12. Crews are working on a storm sewer drain as part of the street widening project.

08/19/2024 UPDATE: Beginning Wednesday, August 21, 2024 Westmore Dr will be closed until May 2025.  The project construction manager has recognized potential safety concerns and has advised the City of Moore to close the street.

07/23/2024  Beginning Tuesday evening after 8:00pm, the Contractor performing the construction for the Widening of 149th Street in OKC from Santa Fe to Western will be closing lanes at the intersection of SW 19th St. and Santa Fe Ave. in Moore.  For Westbound traffic at the intersection, the existing left turn lane will be closed.  The existing westbound thru lane will be used for thru traffic as well as the left turn lane for traffic turning south during construction.  For Eastbound traffic at the intersection, the existing left turn lane will be closed.  The existing outside eastbound lane will be used for thru traffic as well as the left turn lane for traffic turning north.  The existing inside eastbound lane will now become the westbound lane for thru traffic.  Double yellow striping will separate the eastbound and westbound traffic west of the intersection during construction.  It is anticipated that construction will take approximately 8 months to complete.  Any questions regarding the project should be addressed with the OKC Project Construction Manager at 405-297-1768 or [email protected]

Update: 5/15/2025 Briarhill Dr is open!  Crews are finishing up and sod will be laid next week.

Update: 5/8/2025 Briarhill should be opened next Thursday, May 15, weather permitting.

Update: 4/17/2025 The Briarhill box has been poured and crews are now backfilling.  The next step will be street paving and cure time for the bridge.  The project should be completed in 2 weeks, weather permitting.

Update: 4/10/2025 Crews are pouring the bridge deck this morning.  The project should be completed 3 weeks from today, weather permitting.

Update: 3/31/2025 Progress is being made.  Crews will be pouring the walls tomorrow.  Approximate opening date will be 5 weeks, weather permitting.

Update: 3/13/2025 Briarhill remains closed.  The estimated time of reopen is end of April, weather permitting.

Briarhill is closed between NE 19th & NE 20th for an indefinite period of time due to bridge failure.
 

06/09/2025: SE 12th & S Eastern eastbound lanes on SE 12th Street will be closed for approximately 60 days to improve the grade change.  Eastern Ave will remain open during this project.

05/15/2025: Sam's Club, Taco Bell, Braum's, & McDonald's- Crews will be installing a new sewer main & 2 manholes in this area. This project will take about 2 weeks, weather permitting.

05/13/2025: Arnold Street- Arnold St is being totally reconstructed from NW 5th St to NW 2nd St.  Project will be 3 weeks, weather permitting.
05/22/2025: UPDATE-  The west side of Arnold has been poured and it drying curing.  It will be open Tuesday, May 27, 2025.  Crews will begin on the east side after the west side is open.
06/02/2025:  UPDATE- The west side is open and the east will be closing on June 2.  It will remain closed for 2 weeks, weather permitting.

05/08/2025: Phillips Blvd.- Concrete panels will be replaced on both sides starting May 12th.  Phillips Blvd will remain open.  Estimated completion date is 2 weeks, weather permitting.
UPDATE: 05/15/2025- Progress is being made.  Still a couple of weeks out to complete the project, weather permitting. 
05/22/2025: UPDATE-  Phillips Blvd is completed and is curing.  Phillips Blvd. will open on Friday, May 23, 2025.
05/29/2025: Completed

05/22/2025: Norman St, Phase II- NW 2nd St to Main St will be partially closed for reconstruction.  The road will remain open during construction.

03/15/2025- Sunrise Dr- Crews will be installing new water main lines on Sunrise Dr, NW 24th St, N Janeway Ave & Vermeer Dr. This project is expected to be complete by July 30, 2025, weather permitting. 

Buck Thomas Park Softball Fields:
05/22/2025- Crews will be working on drainage issues for the softball fields.  Construction is set to begin at the beginning of summer 2025, weather permitting.

Buck Thomas Park Football Fields:
05/08/2025- Crews will be working on drainage issues for the football fields at Buck Thomas Park.  Construction is set to begin the beginning of June 2025 with the completion date set for the end of June 2025, weather permitting. 

Kiwanis Park:
05/08/2025- Crews will be working on adding a sidewalk from the parking lot directly to the front entrance of the pickle ball courts.  The Crews will also be making sidewalk repairs in front of the Brand Senior Center.  Construction is set begin by the end of May 2025 with the completion date set for mid- June 2025, weather permitting.

Urbansky Farms; nearest intersection is S.E. 19th & Sunnylane Rd.
Update: 05/15/2025- Bridge work is completed.  Crews will be pouring drainage channel for the pond overflow.

Cypress Creek; nearest intersection is S.E. 19th & Sunnylane Rd.
Update: 04/10/2025- Crews are pouring the approach on SE 19th St

Flicker Ridge; nearest intersection is N.E. 12th & Flicker Ridge.
Update: 05/15/2025- Sewerlines will be installed this week.

Broadmoore Heights; nearest intersection is S.E. 34th & S Bryant Ave.